Tuesday, March 4, 2025

Another day full of activity.....

A few of the ladies taught a sewing class to some community ladies - they went home with some hair scrunchies.  ðŸ˜€




More work was done on preparing to hang some gutters.




Chuy and the youth went out in the afternoon to deliver 4 food hampers and pray for those families.



Trenches were dug, and the water project was tested right at the end of the day.....and there was water coming out at the end of the pipe.  ðŸ˜€




The welding shop was non-stop work all day.....but you'll be happy to know, that they are incident free for 2 days in a row now!  Safety first on this job site.


A few progress pics of the adult Sunday School building rebuild.  Finished putting the walls up, and ended the day with 4 of the 6 roof trusses up and secure.




The day ended with a team meal out with the Jimenez family.  What a wonderful family.  ðŸ˜€


Thanks for praying everyone.  Things are going well.  